	<title>Cesar E. Chavez Memorial Building Modernization</title>
	<atom:link href="http://www.chavezmodernization.com/feed/" rel="self" type="application/rss+xml" />
	<link>http://www.chavezmodernization.com</link>
	<description></description>
	<lastBuildDate>Thu, 17 May 2012 13:48:50 +0000</lastBuildDate>
	<language>en</language>
	<sy:updatePeriod>hourly</sy:updatePeriod>
	<sy:updateFrequency>1</sy:updateFrequency>
	<generator>http://wordpress.org/?v=3.1.1</generator>
		<item>
		<title>Thursday May 17 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=thursday-may-17-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/#comments</comments>
		<pubDate>Thu, 17 May 2012 13:48:50 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=874</guid>
		<description><![CDATA[Possible Smells: Today: Paint: 8 south final coats, primed walls on 7 south Welding in the new lobby on the ceiling of the 2nd floor during the day. Painting: 7th floor Friday:Welding in the lobby from 5:00 pm to 3:30 &#8230; <a href="http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Possible Smells:</strong></p>
<ul>
<li>Today: Paint: 8 south final coats, primed walls on 7 south</li>
<li>Welding in the new lobby on the ceiling of the 2nd floor during the day.</li>
<li>Painting: 7th floor</li>
<li>Friday:Welding in the lobby from 5:00 pm to 3:30 am</li>
</ul>
<p><strong>Tenant Relocation:</strong></p>
<ul>
<li>9th and 3rd Floor South: Wednesday May 23 at 9:30 am</li>
</ul>
<p><strong>Update of Construction From Last Night:</strong></p>
<ul>
<li>worked on removal of barriers on the north east corner of the building.</li>
<li>worked on 9th floor east tie back framing and door frame install, tape and finish on 8,7,6 east, framing of damper walls on 3rd floor restrooms, drywall 6 east tie backs, grid on 3 east, drywall on 6 east tie backs, grid on first floor.</li>
<li>worked on heads on 7 south, first floor sprinkler lines, heads on 6 south</li>
<li>worked on fire damper install on 3rd floor,</li>
<li>7thfloor west and south GRD’s,</li>
<li>above ceiling punch on 7 west and south, low pressure duct on 1st floor, off set elbows on duct on the 9th floor</li>
<li>worked on duct replacement on 8th floor at boxes 8-5,8-4,8-2, measure for duc ton 6 east</li>
<li>worked on dust and clean throughout</li>
<li>worked on secure room electrical above ceiling 8th floor north,</li>
<li>worked on power for furniture move backs on 3 north,</li>
<li>lighting rough in 3 east,</li>
<li>HVAC power 8 north,</li>
<li>7th floor above ceiling punch list</li>
<li>worked on fire alarm trim and devices on 7 east and elevator lobbies east all floors</li>
<li>worked lobby stone demo on second floor</li>
<li>worked on 8 south final coats, primed walls on 7 south</li>
<li>worked on stool sill touch up on 3 south, 9 south</li>
</ul>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Tuesday May 15 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=tuesday-may-15-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/#comments</comments>
		<pubDate>Tue, 15 May 2012 14:08:48 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=846</guid>
		<description><![CDATA[Update of Construction from Last Night: drywall on 6 east, drywall on 7 east tie backs, started grid on first floor fitness, tape and finish on 8 east, tape and finish on 7 east, drywall on 6 east, started shooting &#8230; <a href="http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>drywall on 6 east,</li>
<li>drywall on 7 east tie backs,</li>
<li>started grid on first floor fitness,</li>
<li>tape and finish on 8 east,</li>
<li>tape and finish on 7 east,</li>
<li>drywall on 6 east,</li>
<li>started shooting wires and installing wall angle on 3 east,</li>
<li>tape and finish on 6 south</li>
<li>worked on 6th floor west and 8 south sprinkler heads.</li>
<li>worked on 8th floor room V.A.V.s and duct,</li>
<li>damper install on 3rd floor,</li>
<li>worked on controls for the 8th floor room V.A.V.s</li>
<li>worked on 8th floor room duct demo and replacement, FPVAV 8-5</li>
<li>worked on dust and clean throughout building and final clean of 6 and 7 west.</li>
<li>worked on disconnects on 9th floor,</li>
<li>6th floor south lighting, fire alarm &amp; power across 9th floor lobby for dampers,</li>
<li>worked on 3rd floor punch,</li>
<li>9th floor south punch, started painting locker room ceiling</li>
</ul>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Friday May 11 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=friday-may-11-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/#comments</comments>
		<pubDate>Fri, 11 May 2012 13:45:02 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=844</guid>
		<description><![CDATA[Update of Construction from Last Night: worked on pre-punch list for tomorrow’s 3rd floor south walk, pre-punch on 9 south, punch items from 7th and 6th west, worked with prestige for furniture move backs. worked on demo for damper replacements, &#8230; <a href="http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>worked on pre-punch list for tomorrow’s 3rd floor south walk,</li>
<li>pre-punch on 9 south,</li>
<li>punch items from 7th and 6th west,</li>
<li>worked with prestige for furniture move backs.</li>
<li>worked on demo for damper replacements,</li>
<li>drywall on 6 east,</li>
<li>drywall on 7 east,</li>
<li>tape and finish on first floor fitness,</li>
<li>sanding on 9 east,</li>
<li>tape and finish on 8 east,</li>
<li>started tape and finish on 7 east,</li>
<li>sanded drywall in judges office on 6 north west for wall paper,</li>
<li>worked on patches and pre-punch on 3 south,</li>
<li>rebuild framing for damper in level 2 men’s room,</li>
<li>worked on 6th floor west and 8 south sprinkler heads.</li>
<li>worked on 8th floor south GRDs, box 8-1 install,</li>
<li>exhaust damper install in womens and mens room on 2ndfloor,</li>
<li>duct patching on 3 east.</li>
<li>9th floor east HVAC controls,</li>
<li>worked on duct replacement to box 9-27, 8-12,</li>
<li>duct for fire damper on 9th floor</li>
<li>Cleaning employees worked on dust and clean throughout building and final clean of 6 and 7 west.</li>
<li>worked on lights on 6 south west,</li>
<li>3 south wall trim out, lighting on 7 south, power through lobbies on 8 &amp; 9 for new damper install,V.A.V. disconnects on 9, rough in tie back walls,</li>
<li>worked on ceiling demo on second floor lobby,</li>
<li>8th floor east ceiling demo.</li>
<li>9th floor south final coats and touch ups, 3rd floor south</li>
</ul>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Thursday May 10 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=thursday-may-10-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/#comments</comments>
		<pubDate>Thu, 10 May 2012 13:46:10 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=842</guid>
		<description><![CDATA[2 of 14,846 Thursday May 10 Project Update Jennifer Beck (8PSD) 7:37 AM (3 minutes ago) Reply to bcc: &#38;R08, bcc: Chavez Today&#8217;s Vendor: Mary Kay Where: 4th floor Vending area Time; 11:00 am to 2:00 pm Building Heating and &#8230; <a href="http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p>2 of 14,846</p>
<p>Thursday May 10 Project Update</p>
<p>Jennifer Beck (8PSD)</p>
<p>7:37 AM (3 minutes ago)</p>
<p>Reply</p>
<p>to bcc: &amp;R08, bcc: Chavez</p>
<p>Today&#8217;s Vendor:</p>
<p>Mary Kay</p>
<p>Where: 4th floor Vending area</p>
<p>Time; 11:00 am to 2:00 pm</p>
<p><strong>Building Heating and Cooling system Outage:</strong></p>
<ul>
<li>When: 6:00 pm May 11 through 10:00 am May 13</li>
<li>What: Building Air Supply. So no cooling, heating, or recirculated air.</li>
<li>Items Not affected: IT Server Rooms and electrical</li>
</ul>
<p><strong>Electrical Outage: Floor 6, 7 and 8 Only</strong></p>
<ul>
<li>Estimated for June 2: 8:00 am to 5:00 pm</li>
<li>Why: Installation of new HVAC units for zoning</li>
</ul>
<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>worked on removing and replacing door to women’s restroom during damper work to protect the door,</li>
<li>walked pre-punch list on 8th floor above ceiling and worked on demo of old above ceiling wall track,</li>
<li>walked pre-punch on 3 south arch, 9 south arch, 7 west arch, 6 west arch. </li>
<li>worked on dropping ceiling tile on 9 west,</li>
<li>grid on 6 south,</li>
<li>dropped tile in 785 secure room,</li>
<li>tape and finish on first floor for painter to start,</li>
<li>9 east sanding (ready for prime and first coats),</li>
<li>tie back drywall on 7 east,</li>
<li>demo in restrooms for dampers,</li>
<li>patched through wall holes above ceiling from duct removal on 8 west conference rooms,</li>
<li>fixed grid in 8 west conference room,</li>
<li>dry wall on 6 east ready,</li>
<li>worked on 8th floor west and south heads,  </li>
<li>worked on damper install on 2 mens rest room,</li>
<li>tie in return damper on 2nd floor,</li>
<li>VAV install 9-27,9-28,9-29, grds and slots on 8 west, 6 west and 7 west,</li>
<li>worked on V.A.V. controls on 6, controls at 8-15,  </li>
<li>worked on duct replacement and insulation at boxes 9-3, 9-7,</li>
<li>measured and duct install to boxes 9-27,28,29.</li>
<li>worked on dust and clean throughout building.</li>
<li>worked on reconfiguring lights on 9 west and south,</li>
<li>disconnect install on 9 FPVAVs, reconnect power to box 8-15,</li>
<li> lights install on 7 south,</li>
<li>F.A. rough in 6 south,</li>
<li>above ceiling pre-punch on 8 west.</li>
<li>remove all old ceiling supports and anchors in 8 west ceiling,</li>
<li>carpet demo on 7 south west for Décor.</li>
<li>worked on final coats on 6th floor west, 7th floor west, 3rd floor s.west, 9 south 7,6 west, 3 south, 9 south.</li>
<li>worked on carpet install on 7 south, pre-punch on 9 south.</li>
<li>worked on stool sill touch ups on 6 and 7 west. Almost done on west.</li>
</ul>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Wednesday May 9 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=wednesday-may-9-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/#comments</comments>
		<pubDate>Wed, 09 May 2012 15:13:19 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=839</guid>
		<description><![CDATA[Fire Protection Flow Test in Garage: Cancelled. This work will be rescheduled: TBD  Ceiling Demolition · 8th Floor East: Week of May 9-10 · 6th Floor East: Week of May 14 · 7th Floor East: Revised Schedule coming soon.  Note: &#8230; <a href="http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Fire Protection Flow Test in Garage:</strong> Cancelled. This work will be rescheduled: TBD</p>
<p> <strong>Ceiling Demolition</strong></p>
<p>· 8th Floor East: Week of May 9-10</p>
<p>· 6th Floor East: Week of May 14</p>
<p>· 7th Floor East: Revised Schedule coming soon.</p>
<p> Note: Ceiling tile will be coming soon!! Starting on West, South, East and then North.</p>
<p> <strong>Tenant Move schedule:</strong></p>
<p>· 7th and 6th Floor West: Office Shifts May 10 at 6:00 pm.</p>
<p>· Tenant Move: May 14 at 6:00 am.</p>
<p>· 3rd Floor West and South: May 18th at 6:00 am.</p>
<p>· 9th Floor South: May 23rd at 6:00 am.</p>
<p>· 8th Floor South: June 1st at 6:00 am.</p>
<p><strong>Exterior:</strong></p>
<p>· New grass and trees will be coming soon to the garage landscaping.</p>
<p><strong>Schedule:</strong></p>
<p>4 week look-a-head: <a class="downloadlink" href="http://www.chavezmodernization.com/wp-content/plugins/download-monitor/download.php?id=129" title=" downloaded 17 times" >Week of May 7 Schedule (17)</a></p>
<p>Tenant Relocation Schedule: <a class="downloadlink" href="http://www.chavezmodernization.com/wp-content/plugins/download-monitor/download.php?id=130" title=" downloaded 14 times" >Tenant Relocation Schedule (14)</a> </p>
<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>Tile got dropped on the north half of the west side of 9.</li>
<li>Secure room 785 is inspected and ready for ceiling tile to drop Wednesday night at 5:00 P.M.</li>
<li>worked on replacing railing in 7thfloor hearing room,</li>
<li>walked pre-punch on 6 and 7 west, 9,3 south,</li>
<li>worked on dropping ceiling tile on 9 west,</li>
<li>grid on 6 south,</li>
<li>tape and finish 9th floor cubicle wall,</li>
<li>tape and finish 6 south,</li>
<li>Tape and finish 9 east,</li>
<li>tape and finish touch up on 3 east and 3 south,</li>
<li>Tie back walls on 7 east, 8 east.</li>
<li>worked on 7th floor north west heads, secure room 785 heads.</li>
<li>V.A.V. install 8-15,</li>
<li>GRDS on 6 west and south.</li>
<li>worked on fixing temperature controls for box 9-14,</li>
<li>6th floor FPVAV controls in south west corner existing box,</li>
<li>worked on duct demo and reinstall at boxes 9-5, 9-6, 9-26 rezone,</li>
<li>insulated duct in 9 south east.</li>
<li>worked on dust and clean throughout building.</li>
<li>worked on lights on 7 south,</li>
<li>data cable re-route on 9 east conference room, lights in secure room 785,</li>
<li>worked on ceiling demo on first floor lobby</li>
<li>worked on final coats on 6th floor west, 7th floor west, 3rd floor s.west, 9 west at Curtis cubicle, walked pre punch on 7,6 west, 3 south, 9 south.</li>
<li>worked on carpet install on 3 east, carpet removal in 7 hearing room, pre-punch on 6,7, west, 3 south, 9 south.</li>
<li>worked on stool sill install on 6 east, 6th floor west and 7th floor west sill touch up.</li>
</ul>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Tuesday May 8 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/08/tuesday-may-8-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=tuesday-may-8-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/08/tuesday-may-8-project-update/#comments</comments>
		<pubDate>Tue, 08 May 2012 14:58:02 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=835</guid>
		<description><![CDATA[Fire Protection Flow Test in Garage: Where: Garage top floor, but water may flow down the ramps of the garage. When: Wednesday May 9 Time: 8:00 am What: fire protection flow test in the garage. GEJ will block the deck &#8230; <a href="http://www.chavezmodernization.com/2012/05/08/tuesday-may-8-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Fire Protection Flow Test in Garage:</strong></p>
<ul>
<li>Where: Garage top floor, but water may flow down the ramps of the garage.</li>
<li>When: Wednesday May 9</li>
<li>Time: 8:00 am</li>
<li>What: fire protection flow test in the garage. GEJ will block the deck of the parking garage around the fire protection riser. The test is expected to start around 8:00 and shouldn’t last for more than 1 hour total. During the test we will make every effort to control the water from cascading through the garage but there will be incidental water running down the ramps.</li>
</ul>
<p><strong>Ceiling Tiles:</strong></p>
<ul>
<li>Ceiling Tiles will be dropped in sooner than later with the exception of some areas for inspection and hallways.</li>
<li>Therefore, you will start to see ceiling tiles go in next week on the West side 9th floor down and then following will be the South, East and then North. Unfortunately the North Tiles will be out longer then the other sides so that work can be completed on the duct work. This is due to late award of this work and we will have to go back to finish.</li>
</ul>
<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>worked on getting 785 above ceiling work started at 3:00 P.M. with subs</li>
<li>worked on demo for damper replacement on 3, 9,8, 7,</li>
<li>framed return damper wall on 2nd foor east above ceiling,</li>
<li>removed and replaced grid ceiling on 9 for box 9-6,</li>
<li>worked on grid on 6 south west,</li>
<li>framing on 6 east,</li>
<li>tie back walls on 8 east,</li>
<li>installed grid in secure room 785,</li>
<li>tape and finish on 6 south,</li>
<li>touch up finish on 6 and 7 west for final coats,</li>
<li>worked on 9th floor west patch at cubicle (ready for paint Tuesday night and cubicle put back on Thursday),</li>
<li>touch up and thermostat patches on 3 south west.</li>
<li>worked on adjusting head heights on 9thfloor west and south,</li>
<li>dropping heads on 6 east soffit,</li>
<li>heads will be complete in 7th floor north west corner Tuesday night.</li>
<li>worked on install of box 9-6, removed old transfer duct from 9th floor ceilings, install flex duct at box 9-9, replaced old pneumatic damper above room 902,</li>
<li>installed damper through 3rd floor elevator shaft,</li>
<li>installed slot diffuser in 9th floor conference room,</li>
<li>installed slots in 7th floor west (slots in 6th floor west will be complete tomorrow night,)</li>
<li>worked on fixing temperature controls (T-Stats) on 9 west and HVAC controls on 9.</li>
<li>worked on duct removal and replacement in secure room 785,</li>
<li>Install duct to boxes 9-29, 9-26, 9-4,9-2.</li>
<li>worked on final clean on 8 west, dust and clean throughout the building.</li>
<li>worked on lights on 7 south, 6th floor west trim, 6 east rough in at tie backs, damper and fire alarm rough in on 2, safe off of lights in secure room 785.</li>
<li>worked on furniture move back on 8 west.</li>
<li>worked on ceiling demo in secure room 785, ceiling demo on first floor lobby</li>
<li>worked on final coats on 6th floor west, 7th floor west, 3rd floor s.west</li>
<li>worked on carpet install on 3 east.</li>
</ul>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/08/tuesday-may-8-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Thursday May 3 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/03/thursday-may-3-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=thursday-may-3-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/03/thursday-may-3-project-update/#comments</comments>
		<pubDate>Thu, 03 May 2012 13:57:42 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=832</guid>
		<description><![CDATA[Garage Reminder: The garage is secured to meet HSPD-12 guidelines. Therefore, no employees are to drive in behind someone without entering your own ID card. Employees must wait for the garage to close and then use your own card to &#8230; <a href="http://www.chavezmodernization.com/2012/05/03/thursday-may-3-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Garage Reminder:</strong></p>
<ul>
<li>The garage is secured to meet HSPD-12 guidelines. Therefore, no employees are to drive in behind someone without entering your own ID card. Employees must wait for the garage to close and then use your own card to open the door. If you are having issues with your badge, then please contact GSA.</li>
<li>Please note that not all employees have access to the roll up garage door. Those that do not, are employees who just need access to the GOV cars. These employees must use the intercom system to have the guards let them in.</li>
</ul>
<p><strong>Installation of Ceiling Tiles:</strong></p>
<ul>
<li>GSA has received approval to install ceiling tiles after the completion and inspections of the new fire suppression work. Therefore, tenants will begin to see installation of tiles from the West phase, to the South, East and then North. The contractors will have to back track to the North phase due the timing of the additional duct replacement scope of work.</li>
<li>9th floor West and South are coming soon!</li>
</ul>
<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>﻿Room 843 ceiling tile is complete. We might have some top of wall patching and painting which can be done the week of the 21st.</li>
<li>worked on punch list above ceiling 9th floor and 7th floor west pre-punch.</li>
<li>worked on completing ceiling tile in 843,</li>
<li>dropped ceiling tile on 3 west and south ( 3 South ceiling tile should be complete by end of shift Thursday night),</li>
<li>framing on the 6th floor east</li>
<li>drywall on 7th floor east,</li>
<li>final touch ups on 6th floor south (ready for paint by Monday night),</li>
<li>final touch ups for final coats on 6 south ( Final paint Thursday night after patches get sanded first thing),</li>
<li>patches on 3rd floor south west at green wall (ready for final coats on green wall end of Shift Thursday night),</li>
<li>tape and finish on 9 east.</li>
<li>worked on fire sprinkler 8th floor west heads,</li>
<li>9th floor south sprinkler heads which will be complete by end of shift tomorrow night.</li>
<li>worked on 9th floor west and south GRDS,</li>
<li>worked on new damper install on 2nd floor</li>
<li>worked duct demo and re-install to the HVAC boxes above ceiling in the 7th floor lunch room,</li>
<li>worked on dusting and cleaning office spaces throughout the building.</li>
<li>worked on Lighting on 8 south, 7 south,</li>
<li>power to V.A.V.s on 9 south and east,</li>
<li>worked on 9th floor fire alarm trim west and south, pulling wire on 8 south.</li>
<li>worked on ceiling demo on 3rd floor east (complete).</li>
<li>worked 7,8 floor west final coats and pre-punch.</li>
<li>6th floor west will get final coats tomorrow night after sanding of patches.</li>
<li>worked on 7th floor west touch ups of stool sill, stool sill install on 6 east.</li>
</ul>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/03/thursday-may-3-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Tuesday May 1 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/05/01/tuesday-may-1-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=tuesday-may-1-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/05/01/tuesday-may-1-project-update/#comments</comments>
		<pubDate>Tue, 01 May 2012 14:27:41 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=827</guid>
		<description><![CDATA[Joint Use Phones: Due to internet issues, the Joint Use Conference Room phones are still not working. We hope to have this resolved this morning. Sorry for the inconvenience. Update of Construction from Last Night: - worked on preparing tie &#8230; <a href="http://www.chavezmodernization.com/2012/05/01/tuesday-may-1-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Joint Use Phones:</strong></p>
<ul>
<li>Due to internet issues, the Joint Use Conference Room phones are still not working. We hope to have this resolved this morning. Sorry for the inconvenience.</li>
</ul>
<p><strong>Update of Construction from Last Night:</strong></p>
<p>- worked on preparing tie back walls on 8 east,</p>
<p>- frame 6 east,</p>
<p>- tape and finish 6 south,</p>
<p>- sand and touch up 8th floor,</p>
<p>- sand and touch up 6th floor north west,</p>
<p>-Grid on 8th floor in rm 843, border tiles and trim tiles on 3rd floor west, 8th floor west.</p>
<p>- worked on dropping heads in 7th floor east soffits,</p>
<p>- Tomorrow night will work on ceiling and V.A.V. demo in the restrooms.</p>
<p>- worked on 9th floor west re-zoning and removed old medium pressure fire dampers and replaced with duct (2 locations)</p>
<p>- worked on priming walls in 8th floor north west office, 8th floor west conference room,</p>
<p>- prime and paint 3rd floor east.</p>
<p>-worked on dusting and cleaning office spaces throughout the building.</p>
<p>-worked on lighting controls on 8th floor south lighting,</p>
<p>-Fire alarm rough in on 7 south,</p>
<p>- 6 south fire alarm rough in and demo of old.</p>
<p>- Caulked penetrations above ceiling outside the conference room on 3 south.</p>
<p>- worked on finishing fire alarm on 3 west and south for above ceiling final today.</p>
<p>-worked on ceiling demo in the level 2 elevator lobby,</p>
<p>-ceiling demo inside and outside room 843 as scheduled.</p>
<p>- Tomorrow night they should be removing ceilings in 3rd floor east.</p>
<p>- worked on priming walls in 8th floor north west office, 8th floor west conference room,</p>
<p>-prime and paint 3rd floor east.</p>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/01/tuesday-may-1-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Monday April 30 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/04/30/monday-april-30-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=monday-april-30-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/04/30/monday-april-30-project-update/#comments</comments>
		<pubDate>Mon, 30 Apr 2012 21:35:55 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=824</guid>
		<description><![CDATA[Bonfils Blood Drive: TODAY Room 413 8:30 am Yoga: TODAY 12:00 Location CHANGE: GAO 8th floor Conference Room (west side) Update from Friday Nights Construction: -worked on drywall skimming where wall paper was removed in 8th floor north west office, &#8230; <a href="http://www.chavezmodernization.com/2012/04/30/monday-april-30-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Bonfils Blood Drive:</strong></p>
<ul>
<li>TODAY</li>
<li>Room 413</li>
<li>8:30 am</li>
</ul>
<p><strong>Yoga:</strong></p>
<ul>
<li>TODAY</li>
<li>12:00</li>
<li>Location CHANGE: GAO 8th floor Conference Room (west side)</li>
</ul>
<p><strong>Update from Friday Nights Construction:</strong></p>
<p>-worked on drywall skimming where wall paper was removed in 8th floor</p>
<p>north west office, 8th floor west conference rooms and 6th floor judge&#8217;s office. Also patched old thermastat locations.</p>
<p>- worked on stool sill touch up paint on 3rd floor west, 2nd floor west.</p>
<p>-worked on water main on 13th street.</p>
]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/04/30/monday-april-30-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>Friday April 27 Project Update</title>
		<link>http://www.chavezmodernization.com/2012/04/30/friday-april-27-project-update/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=friday-april-27-project-update</link>
		<comments>http://www.chavezmodernization.com/2012/04/30/friday-april-27-project-update/#comments</comments>
		<pubDate>Mon, 30 Apr 2012 21:34:57 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=822</guid>
		<description><![CDATA[﻿Update of Construction from Last Night: -worked on completing backing on 8th floor east, -pre punch list on 3rd floor west and south above ceiling, -9th floor punch list. -worked drywall 8 east, -drywall touch up on 8 and 7 &#8230; <a href="http://www.chavezmodernization.com/2012/04/30/friday-april-27-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>﻿Update of Construction from Last Night:</strong></p>
<p>-worked on completing backing on 8th floor east,</p>
<p>-pre punch list on 3rd floor west and south above ceiling,</p>
<p>-9th floor punch list.</p>
<p>-worked drywall 8 east,</p>
<p>-drywall touch up on 8 and 7 west,</p>
<p>-tape and finish on 6 south.</p>
<p>-Dropped tile above Mr. Laetz office for sound on 8th floor.</p>
<p>-worked on dropping heads in 8th floor west ceiling.</p>
<p>-worked on installing grds on 3rd floor west and south to be ready for above ceiling walks.</p>
<p>-worked on insulating new duct on 9th floor west with M-Tech</p>
<p>- worked on 9th floor west re-zoning and removed old medium pressure fire dampers and replaced with duct (2 locations).</p>
<p>-worked on dusting and cleaning office spaces throughout the building,</p>
<p>-final cleaned washed windows on 9th floor west perimeter,</p>
<p>- washed windows on 8th floor west where we did not have masking for wall paint touch ups.</p>
<p>-worked on lighting controls on 3rd floor south powered up cubicle furniture in far north east room on 3 west,</p>
<p>-7th floor east wall rough in,</p>
<p>- 7th floor south fire alarm</p>
<p>- worked on ceiling demo in the level 2 elevator lobby.</p>
<p>-worked on pulling wall paper and prepped for skim coats in 8thfloor north west office,</p>
<p>-8th floor west conference room,</p>
<p>- 6th floor north west judges office,</p>
<p>-first paint coats on 3rd floor east,</p>
<p>-remove masking on 8 west and 7 south.</p>
<p>-worked on carpet and base in 3rd floor south west rooms</p>
<p>-8 floor blinds and punch list.</p>