Wednesday June 20 Project Update

Update of Construction from Last Night:

  • carpenters installed new door closures in the stair ways.
  • worked on finishing grid on 7 east as far as they can go,
  • worked on grid in corridors on 2nd and 3rd floor,
  • drywall ODAR west walls (The wall that needs bumped will get adjusted Wednesday night and rocked),
  • drywalled the east side of 2nd floor,
  • drywalled lids in 2,3 restrooms and started 6th floor lid.
  • Tape and finish followed the lids being rocked,
  • Worked on 6 east GRDs,
  • 9th and 8th floor damper install,
  • layout slot diffusers on 7 east.
  • worked on 6 east lights,
  • light can rough in level 2 lobby,
  • power and fire alarm on 8 & 9 dampers,
  • furniture move back power on 9 east and 8 east.
  • worked on move backs on 9 east (Complete), 8 east.
  • worked on demo of the mother’s den on second floor and demo of walls in 764 hearing room (complete), above ceiling demo on 2nd floor.
  • worked on color coats on 6 and 7 east,
  • walked D.O.J. and goals for final paint tomorrow night. Walked 6 south south east.
  • worked on 7 east sprinkler heads.
  • worked on dusting and general cleaning throughout the floors.
  • worked on final clean of cubicles on 3 east and 9 east.

Project Schedule: Coming later today

This entry was posted in Events.
Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>