Update of Construction from Last Night:
- carpenters installed new door closures in the stair ways.
- worked on finishing grid on 7 east as far as they can go,
- worked on grid in corridors on 2nd and 3rd floor,
- drywall ODAR west walls (The wall that needs bumped will get adjusted Wednesday night and rocked),
- drywalled the east side of 2nd floor,
- drywalled lids in 2,3 restrooms and started 6th floor lid.
- Tape and finish followed the lids being rocked,
- Worked on 6 east GRDs,
- 9th and 8th floor damper install,
- layout slot diffusers on 7 east.
- worked on 6 east lights,
- light can rough in level 2 lobby,
- power and fire alarm on 8 & 9 dampers,
- furniture move back power on 9 east and 8 east.
- worked on move backs on 9 east (Complete), 8 east.
- worked on demo of the mother’s den on second floor and demo of walls in 764 hearing room (complete), above ceiling demo on 2nd floor.
- worked on color coats on 6 and 7 east,
- walked D.O.J. and goals for final paint tomorrow night. Walked 6 south south east.
- worked on 7 east sprinkler heads.
- worked on dusting and general cleaning throughout the floors.
- worked on final clean of cubicles on 3 east and 9 east.
Project Schedule: Coming later today
January 19, 2012
April 30, 2012