Tuesday February 14 Project Update

Schedule Update:

2nd & 3rd Floor:

This Week: Feb 13-17

  • North: Completing Punch List Items
  • West: Drywall installation and then prime and first coat on perimeter Feb 13/14
  • West: Removal ceiling tile and grid. Raise and support ceiling equipment. Removing abandoned equipment and install new HVAC controls. Feb 13-16

Next Week Feb 21-24

  • North: 2nd Floor Cubicle Installation: Estimated Feb 23
  • West: Remove Plastic on perimeter and prime and first coat Feb 20
  • West: Install new grid Feb 22/23

9th Floor:

This Week: Feb 13-17

  • North: Install ceiling tile borders and devices Feb 15/16
  • West: Tape and finish drywall Feb 13-16

Next Week Feb 21-24

  • North: Final Paint: Feb 20-21
  • North: Installation of window shades: Feb 23
  • West: Remove Ceiling Tile and Grid: Feb 22/23

8th Floor:

This Week: Feb 13-17

  • North: Install ceiling tile borders and devices: Feb 15/16
  • West: Framing walls, electrical rough in and hanging drywall. Feb 14/15

Next Week Feb 21-24

  • North: Installation of sprinkler covers and window soffit work. Feb 20-23
  • West: Tape and finish drywall Feb 20-23

NOTE: Ceiling Tile Removal West: Starts Feb 29

7th Floor:

This Week: Feb 13-17

  • North: Install carpet and Base All week
  • West: Framing walls, electrical rough in and hanging drywall. All week

Next Week Feb 21-24

  • North: Install ceiling tile borders and devices, rework window soffit Feb 20-21
  • West: Framing walls, installing window sills and hanging drywall along perimeter.

6th Floor:

This Week: Feb 13-17

  • North: Nothing this week
  • West: Nothing this week

Next Week Feb 21-24

  • North: Install ceiling tile borders and devices, rework window soffit Feb 22-23
  • West: Framing walls, electrical rough in and installing window sills. Feb 20-23

Elevator Outages:

  • Two elevators out of service full time: March 12
  • Until then, daily outages for two elevators from 9:00 am to 5:30 pm for preparation work.

Exterior Work:

  • Removal of Barrier Walls: South Levels 2-9: Feb 20-24
  • Installation of curtain walls: East (SE Side) Levels 2-9 Feb 20-Mar 27
  • Installation of clips and metal angles on East (NE side): Feb 13-16

Electrical Outage: March 3-4

  • We will get more information on the outage in less than a week. This outage will consist of 1-2 floors at a time and time slots will be given for each agency.

Garage Pedestrian Door Canopy:

  • Many of you have expressed concern over the leaking water on your heads while accessing the pedestrian door at the garage. GSA is working to install a roof drain, however, the current design is with the City of Denver for approval. Once approved, this will be corrected. Thank you for your patience.

This entry was posted in Events.
Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>