Schedule Update:
2nd & 3rd Floor:
This Week: Feb 13-17
- North: Completing Punch List Items
- West: Drywall installation and then prime and first coat on perimeter Feb 13/14
- West: Removal ceiling tile and grid. Raise and support ceiling equipment. Removing abandoned equipment and install new HVAC controls. Feb 13-16
Next Week Feb 21-24
- North: 2nd Floor Cubicle Installation: Estimated Feb 23
- West: Remove Plastic on perimeter and prime and first coat Feb 20
- West: Install new grid Feb 22/23
9th Floor:
This Week: Feb 13-17
- North: Install ceiling tile borders and devices Feb 15/16
- West: Tape and finish drywall Feb 13-16
Next Week Feb 21-24
- North: Final Paint: Feb 20-21
- North: Installation of window shades: Feb 23
- West: Remove Ceiling Tile and Grid: Feb 22/23
8th Floor:
This Week: Feb 13-17
- North: Install ceiling tile borders and devices: Feb 15/16
- West: Framing walls, electrical rough in and hanging drywall. Feb 14/15
Next Week Feb 21-24
- North: Installation of sprinkler covers and window soffit work. Feb 20-23
- West: Tape and finish drywall Feb 20-23
NOTE: Ceiling Tile Removal West: Starts Feb 29
7th Floor:
This Week: Feb 13-17
- North: Install carpet and Base All week
- West: Framing walls, electrical rough in and hanging drywall. All week
Next Week Feb 21-24
- North: Install ceiling tile borders and devices, rework window soffit Feb 20-21
- West: Framing walls, installing window sills and hanging drywall along perimeter.
6th Floor:
This Week: Feb 13-17
- North: Nothing this week
- West: Nothing this week
Next Week Feb 21-24
- North: Install ceiling tile borders and devices, rework window soffit Feb 22-23
- West: Framing walls, electrical rough in and installing window sills. Feb 20-23
Elevator Outages:
- Two elevators out of service full time: March 12
- Until then, daily outages for two elevators from 9:00 am to 5:30 pm for preparation work.
Exterior Work:
- Removal of Barrier Walls: South Levels 2-9: Feb 20-24
- Installation of curtain walls: East (SE Side) Levels 2-9 Feb 20-Mar 27
- Installation of clips and metal angles on East (NE side): Feb 13-16
Electrical Outage: March 3-4
- We will get more information on the outage in less than a week. This outage will consist of 1-2 floors at a time and time slots will be given for each agency.
Garage Pedestrian Door Canopy:
- Many of you have expressed concern over the leaking water on your heads while accessing the pedestrian door at the garage. GSA is working to install a roof drain, however, the current design is with the City of Denver for approval. Once approved, this will be corrected. Thank you for your patience.
–
June 26, 2012



