• CHECK out our new Sustainable Design web page

    Do you want to know how the ARRA major renovation project incorporated LEED features into the building?  Then clink on our new Sustainable Design web page tab above.

  • Tuesday September 25 Project Update

    Window Cleaning: Continuing through next week. Currently on the North Side HVAC and Lighting Commissioning: Starting Oct 15-19. The current schedule is as follows: ( I will be coordinating with each tenant for access to secure spaces) Oct 15: DOED, … Continue reading

  • Tuesday September 25 Project Update

    Fire Alarm Testing: In preparation for the fire alarm testing sign off on Oct 1st, the contractor will be doing more pre-testing this Wednesday and Thursday. Testing will include fire alarm testing of horns and strobes throughout the building starting … Continue reading

  • Thursday September 20 Project Update

    Window Cleaning: The contractor will be cleaning the exterior of the building’s windows. This work will take place the entire week of Sept 24-28. ID Activation: The next day for card activation is October 3 from 7-4. All Stairwells Open: … Continue reading